Telecommunications development
Mobile phones are part of everyday life for many people. As the demand for network coverage increases, so does the need for more masts. The siting of masts is often a contentious matter and generates a great deal of public interest.
There are three categories for telecommunications development. These are permitted development, prior approval and full planning permission. The regulations for these types of development are set out in Part 16 of the Town and Country (General Permitted Development) (England) Order 2015 (GPDO).
Permitted development
Most minor forms of installation are permitted development and do not need planning permission. This includes development such as; the installation of additional antenna on existing masts, equipment cabinets of less than 2.5 cubic metres and all broadband related development and cabinets.
The developer will notify us in writing of their intention to install telecommunications apparatus. Development in this category is permitted by law, and does not require an application to, consultation with, or determination by us. It is the developers responsibility, not ours, to notify property owners of any works.
Prior approval
The installation, alteration or replacement of some types of telecoms apparatus is permitted by planning law, but is subject to a prior approval process for its siting and appearance. This procedure applies to the following:
- development in a conservation area, national park or site of special scientific interest (except for broadband related development)
- a mast
- an antenna which exceeds the height of the building or structure (on which it is installed) by 6 metres or more
- a public call box
- radio equipment housing bigger than 2.5 cubic metres
The prior approval procedure allows us to approve or refuse details of the siting and appearance of the installation. The 'siting' and 'appearance' of the proposal are the only factors that can be considered under an application for prior approval. No other matters can be considered.
Factors concerning siting may involve:
- height of the site in relation to surrounding land
- topography of the site and vegetation
- openness and visibility of the site
- designated areas
- the site in relation to existing masts
- structures or buildings
- proximity to residential property
With regard to appearance this can include details such as:
- materials
- colour
- design
- dimensions
- overall shape
- solid or open framework
We have a strict deadline of 56 days to determine these applications. If we have not notified the applicant of our decision by day 56, the applicant is entitled to carry out the works as submitted.
Full planning permission
Development that does not comply with the GPDO such as; masts over 15m in height, antenna and dishes of over a certain size or number, require full planning permission.
Health considerations
We cannot take health considerations into account when determining mast proposals.
All proposals for telecommunications development should be submitted with an International Commission on Non-Ionising Radiation Protection (ICNIRP) Certificate. This certificate confirms that the mast meets the guidelines for public exposure. Beyond this, the health effects in relation to the development or concerns about them, cannot be considered further by the Local Planning Authority.
The UK Health Security Agency (formerly Public Health England) advises the UK government departments and others on standards of protection for exposure to ionising and non-ionising radiation. They offer expert advice on the health implications relating to human exposure to electromagnetic fields, drawing upon the most up-to-date research world-wide.
The Department of Health have produced a leaflet on mobile phone base stations and health. This outlines some of the measures taken to address health concerns about mobile phone service.
Information on telecommunications development in context with the planning system is provided in the National Planning Policy Framework: chapter 5.
The government's former 'Code of best practice on mobile phone network development' provided guidance to Mobile Network Operators, their agents and contractors, and local planning authorities in England. This guidance has been withdrawn and guidance is now issued by the Mobile Network Operators themselves. Details and links to these documents are on the Code of best practice on mobile network development in England pages on Gov.uk.